FORUMS FORUMS



  
FORUMS > Wakefield Trinity > Box Stadium - Part 2
192 posts in 14 pages 
<<   PREV  NEXT   >>
Subscribe | Moderators: Admin, PopTart , kinleycat , Wildthing
RankPostsTeam
Club Coach8962
JoinedServiceReputation
Oct 200420 years
OnlineLast PostLast Page
May 2022Jun 2021LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Wakefield Trinity Stadium - Newmarket development
Frequently asked questions – April 2017
What is a Unilateral Undertaking?
A Unilateral Undertaking is a form of a Section 106 agreement. It is a legal deed where
developers agree to perform planning obligations. However, unlike Multi-lateral Section 106
agreement it is signed by a single party.
What is a Multi-lateral Undertaking?
A Multi-lateral Undertaking is a form of a Section 106 agreement. It is a legal deed signed
by a number of parties.
What is a Section 106?
A Section 106 is a legal pledge. It can take the form of a Unilateral Undertaking, which is a
commitment by a single party, or a Multi-lateral Undertaking, where a number of parties are
involved.
It can involve funding or land being given to the Council and being used by the Council in
respect of that development.
Normally a Section 106 is agreed between the local authority and a developer when a
development takes place. However, in the case of the Newmarket Development, it was
agreed by the Secretary of State, not the local authority.
Has the Council signed a Section 106 for Newmarket stadium?
No, the developer signed a Unilateral Undertaking and agreed it with the Secretary of State.
We asked for a Multi-lateral Undertaking, however the Secretary of State decided instead to
accept a Unilateral Undertaking, which the developer produced alone. The Council did not
sign this document and is not a beneficiary. The Club and The Trust are fully aware of this.
Why, when planning permission has been granted, has the stadium not been built
yet?
Currently neither of the trigger points, which would require the stadium to be built, have
been reached.
The two triggers that both need to be met are:
1. A funding agreement, to the value of £2m, is reached by, Wakefield and District
Community Trust (the Trust), Wakefield Trinity and Wakefield Council as a collective
or individually to contribute to the cost of building a stadium.
and
2. 60,000 square meters of B8 floor space is occupied on the development site.
Why can’t the Council force the developer to build a stadium?
It is entirely up to the developer how quickly they bring forward development or if all the
development is actually built. Until the point that the triggers, outlined in the Unilateral
Undertaking are met, the Council is unable to force the developer to build a stadium.
Once the triggers have been met, the Council, as the Planning Authority, is fully committed
to taking all legal measures at its disposal to ensure that the developer fulfils the obligations
in the Unilateral Undertaking.
Why does the Newcold development not count toward reaching the 60,000sqm
occupancy set out in the Unilateral Undertaking?
A separate full planning application for the 22,300sqm Newcold development had to be
submitted as the Newcold building did not fall within the parameters of the approved outline
consent issued by the Secretary of State.
By law this meant that it couldn’t be considered as part of the Newmarket development and
separate planning permission needed to be submitted.
Why did the Council approve planning permission for the Newcold development if it
didn’t contribute to meeting the triggers set out in the Unilateral Undertaking? Has
this compromised the Stadium development?
Although Yorkcourt Properties Ltd and Newcold Ltd did not provide a Section 106
agreement linking the Newcold development with the funding for a community stadium, the
development did include the installation of a road infrastructure that will provide essential
access to the proposed location of a new stadium.
The development has also created approximately 154 much needed jobs in the Wakefield
district.
The Newcold development has not compromised the development of a community stadium.
Even if the 22,300sqm facility had contributed to the 60,000sqm B8 development identified
in the Unilateral Undertaking, it would not have triggered the development of a stadium.

RankPostsTeam
International Board Member4933
JoinedServiceReputation
Jan 200322 years
OnlineLast PostLast Page
Nov 2024Nov 2024LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Quote: Wakefield No 1 "Wakefield Trinity Stadium – Wakefield Council position statement April
2017
We have a long, proud history of top-quality sport in the Wakefield district and Wakefield
Council is committed to supporting it to thrive.
Since 1984 the Council has provided Wakefield Trinity Rugby League Club (the Club) with
financial assistance in excess of £1.6m in the form of guarantees, ground works and
amounts written-off by the Council within Company Voluntary Arrangements entered into by
Wakefield Trinity Wildcats in 2000 and again in 2004.
In July 2009 the Council’s Cabinet offered land assets to the value of £2m (subject to
criteria) to both Wakefield District Community Trust and Castleford Tigers on the
understanding that both clubs are in the Super League and need to upgrade facilities to
meet Rugby Football League criteria. In December 2010 the criteria hadn’t been met and
the Council chose to extend its £2m funding offer to July 2011. In July 2011 the criteria still
had not been met and the funding offer expired.
In December 2012, planning permission for a new stadium was granted by the Secretary of
State – a decision that the Council welcomed. The permission was accompanied by a
Unilateral Undertaking. This document was signed by Yorkcourt Properties Ltd (the
developer) and two other landowners and was accepted by the Government’s Planning
Inspector. It was not signed by Wakefield Council.
The Council asked for, and would have preferred, a Multi-lateral Section 106 agreement,
signed by a number of parties including the Council. This would have enabled the local
authority to negotiate clear funding streams and tighter triggers for the development of a
stadium. The decision to accept the developer’s Unilateral Undertaking was that of the
Planning Inspector and ultimately formed part of the planning approval issued by the
Conservative MP Eric Pickles in his capacity as Secretary of State.
The Council is not a party to, or a beneficiary of, the Unilateral Undertaking. The persons
liable to the obligation are those persons with interests in the land only – namely Oldroyd
and Sons, Clydesdale Bank Plc and Yorkcourt Properties Ltd.
The Unilateral Undertaking obliges the developer to let build contracts for the stadium once
two trigger point are reached. These are:
1. A funding agreement, to the value of £2m, is reached by, Wakefield and District
Community Trust (the Trust), Wakefield Trinity and Wakefield Council as a collective
or individually to contribute to the cost of building a stadium.
and
2. 60,000 square meters of B8 floor space is occupied on the development site.
Currently neither of these trigger points, which would require the stadium to be built, have
been reached.
It is entirely up to the developer how quickly they bring forward development, or if the
development is built at all. Until the point that the triggers, outlined in the Unilateral
Undertaking are met, the Council is unable to force the developer to build a stadium.
Once the triggers have been met, the Council, as the Planning Authority, is fully
committed to taking all legal measures at its disposal to ensure that the developer fulfils
the obligations in the Unilateral Undertaking. The Council has never suggested that it will
not enforce these obligations.
The Unilateral Undertaking clearly states that the Trust are the ‘facilitators’ for the delivery
of the stadium.
Since planning permission was granted, Wakefield Council has been actively working to
attract private sector investment and development at Newmarket to help achieve the 60,000
square metres of B8 Warehousing and distribution floor space identified in the Unilateral
Undertaking.
The Trust commenced regular meetings to facilitate the delivery of a community stadium
and the Council attended as an advisor to the Trust. The Council advised the Trust to
establish a contract between themselves, the developer and the Club (as potential tenants)
to facilitate and occupy a community stadium. The Council understand that a draft
agreement was drawn up by the developer for consideration. The Council offered to
continue providing advice on the terms of the contract but this offer was declined by Trust
members in a meeting on 24 March 2015 – an extract of the minutes can be found at the
end of this statement.
In July 2013, a planning application was submitted by Yorkcourt Properties Ltd and
Newcold Ltd for a cold food distribution warehouse within the Newmarket site.
The developer chose to submit a separate full planning application for the 22,300sqm
Newcold development as the Newcold building did not fall within the parameters of the
approved outline consent issued by the Secretary of State. By law this meant that it couldn’t
be considered as part of the Newmarket development and separate planning permission
needed to be submitted.
This was communicated to the Trust at a meeting with the Chief Executive and Corporate
Director for Regeneration and Economic Growth from Wakefield Council at that time.
In line with the Council’s Statement of Community Involvement and statutory regulations,
there were two separate 21-day periods of public consultation relating to the Newcold
development. No objections to the Newcold planning application from the Trust were
received.
In granting planning permission for the Newcold development, the development of a
community stadium has not been compromised. Even if the 22,300sqm facility had
contributed to the 60,000sqm B8 development identified in the Unilateral Undertaking it
would not have triggered the development of a stadium.
Although Yorkcourt Properties Ltd and Newcold Ltd did not provide a Section 106
agreement linking the Newcold Development with the funding for a community stadium, the
development did include the installation of a road infrastructure that provides essential
access to the proposed location of a new stadium. The development has also created
approximately 154 much needed jobs in the Wakefield district.
The Council, during informal conversations with the Trust, has made it clear that it is
prepared to make a financial contribution, similar to the offer made in 2009, as part of the
development of a new stadium at Newmarket. To date, the Trust have not asked the
Council to provide any funding, nor have they shared any details of funding raised from
other avenues to contribute to the development of a new stadium.
Senior Council representatives, including the Leader and Chief Executive, have had
numerous meetings meeting with the Club, the Trust and the developer to help progress the
development of a new community stadium. These meetings have been as recent as last
week with further meetings in the diary. A full chronology of activity relating to the
development of a new community stadium can be found at

so the Council do minute the meetings then?

RankPostsTeam
Club Coach8962
JoinedServiceReputation
Oct 200420 years
OnlineLast PostLast Page
May 2022Jun 2021LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Wakefield Trinity Stadium
Timeline of activity to April 2017
1
Date Activity
April 2009 In preparing the Local Development Framework for Wakefield, the Council
produced a Core Strategy that identified the need to find an additional 95
hectares of land for B8 warehousing and storage uses. The Core Strategy
underwent public examination and was found to be “sound” by an Inspector
appointed by the Secretary of State. It was adopted as policy by the Council
in April 2009.
July 2009 Wakefield Council offered Wakefield and District Community Trust £2m
funding to support the development of new stadiums on the condition they
could deliver the following to Wakefield District Community Trust subject to all legal requirements
being fulfilled. The approval of the transfer at, an undervalue, was agreed by
the Secretary of State and subject to the agreement of terms.
The purpose was to allow in the first instance borrowing against the site to
allow the stadium scheme to commence. The borrowing would be capped at a
maximum of £2million. Cabinet in December 2010 agreed to extend the
current offer of land up to a value of £2 million to the Wakefield and District
Community Trust (Wakefield Wildcats) value subject to the conditions to July
2011.
The offer naturally expired in July 2011 and was not renewed
During and since this time Wakefield Wildcats have been in administration
and has been sold twice.
February
2010
Outline planning application submitted by Yorkcourt Properties for mixed use
development at Newmarket Lane, including the community stadium, business
units, Storage & Distribution units, multi-use games areas, a hotel, a food unit
and associated roads and infrastructure.
March
2010
The Council agreed a loan guarantee with the Co-op Bank on 25 March 2010
for a loan taken out by the Trust for £150k for design fees for a community
stadium
October
2010
Planning & Highways Committee resolution to approve the development at
Newmarket Lane, subject to call-in by the government.
December
2010
As no proposals had been received by Wakefield Trinity, Wakefield Council
extends its £2m funding offer to July 2011.
Wakefield Trinity Stadium
Timeline of activity to April 2017
2
March
2011
The bank called upon the Council (as guarantor) to repay the loan in full.
July 2011 The £2m funding offer expired and was not renewed as the Trust did not
meet the conditions, nor did they ask for a further extension.
December
2011 -
The Secretary of State’s Public inquiry held into the Newmarket Lane
development.
September
2012
Local Development Framework development sites document was adopted by
the Council following a process to identify development sites to meet
additional need for warehousing and storage uses identified in the Core
Strategy. The Newmarket site being one of the sites. The Newmarket site and
other development sites were subject to an examination in public and
subsequently found to be “sound” by the inspector and incorporated into the
adopted Sites Allocations Document.
December
2012
Secretary of State decision made on Newmarket site.
This permission was approved by the Secretary of State following a 3 week
call in Inquiry. That permission was accompanied by a Section 106 Unilateral
Undertaking.
The Council were not party to that Unilateral Undertaking which was signed
by Yorkcourt and two other landowners, and set out their intention to let the
Stadium construction contract, provided the finance for the stadium was
available and once 60,000 sq. m of B8 warehousing had been built. A
planning condition was also attached to the Consent issued by the Secretary
of States that states:
“No more than 60,000m2
of the B8 development shall be occupied unless and
until the stadium is completed to its design capacity of 12,000 so as to be
capable of staging a Rugby Super League match attended by the public and
the stadium and its ancillary elements have received all necessary safety and
other certificates to allow it to be used for that purpose.”
The Unilateral Undertaking states that the Wakefield and District Community
Trust are responsible for acting as ‘facilitator’.
A copy of the Unilateral Undertaking can be found here:
cominoweb.wakefield.gov.uk/Plann ... =lg.Planni
ng&org.apache.shale.dialog.DIALOG_NAME=gfplanningsearch&SDescriptio
n=10/00225/OUT&viewdocs=true (Second document).
July 2013 Newcold planning application submitted.
A separate planning application was submitted by Yorkcourt Properties and
Newcold Ltd for a cold food distribution warehouse within the Newmarket site.
Wakefield Trinity Stadium
Timeline of activity to April 2017
3
This was submitted as a separate full planning application and was not linked
to the stadium development proposal that was given consent by the
Secretary of State.
The developer submitted a separate full planning application due to the
proposed size of the Newcold building which did not fall within the parameters
of the approved outline consent issued by the Secretary of State. The
decision to put in a new application was that of the developers not the
council, and the Council as the planning authority were duty bound to
consider a valid application as was the case.
Yorkcourt did not provide a Section 106 Agreement to link the Newcold
development with the funding of a community stadium. This was not required
as the site was allocated for employment uses within the Local Plan. This
was communicated to the Trust at a meeting with the Chief Executive and
Corporate Director for Regeneration and Economic Growth from Wakefield
Council at that time.
In line with the Council’s Statement of Community Involvement and statutory
regulations, there were two separate 21-day periods of public consultation
relating to the Newcold development. No objections to the Newcold planning
application from the Trust were received.
The development of the Newcold building does not prevent the 60,000 sq m
threshold of B8 development being met on the remainder of the site.
The Unilateral Undertaking offered by Yorkcourt and approved by the
Secretary of State, did not prohibit or limit any further planning applications or
development on the site.
The development of the stadium therefore can still be implemented
irrespective of the existence of the Newcold development.
October
2013
Newcold decision issued.
The Planning & Highways Committee made the decision to approve the
Newcold planning application.
The Committee Report on the Newcold proposal made clear, on page 11,
that the application was submitted as a standalone application and was not
covered by the outline planning consent for the stadium development or
planning conditions.
The report is available here.
cominoweb.wakefield.gov.uk/Plann ... =lg.Planni
ng&org.apache.shale.dialog.DIALOG_NAME=gfplanningsearch&SDescriptio
n=13/02001/FUL&viewdocs=true (First document).
Wakefield Trinity Stadium
Timeline of activity to April 2017
4
2015 Newcold development is completed. This includes the installation of a road
infrastructure that will provide essential access to the proposed location of a
new stadium.
The development created approximately 154 full time jobs in the district.
2013-17 Wakefield Council continues to meet with Wakefield Trinity, the Trust and
Yorkcourt to facilitate the progression of a new community stadium.
As part of ongoing work, the Council actively promotes the site to investors
coming into the district.
Wakefield Trinity Stadium
Timeline of activity to April 2017
1
Date Activity
April 2009 In preparing the Local Development Framework for Wakefield, the Council
produced a Core Strategy that identified the need to find an additional 95
hectares of land for B8 warehousing and storage uses. The Core Strategy
underwent public examination and was found to be “sound” by an Inspector
appointed by the Secretary of State. It was adopted as policy by the Council
in April 2009.
July 2009 Wakefield Council offered Wakefield and District Community Trust £2m
funding to support the development of new stadiums on the condition they
could deliver the following to Wakefield District Community Trust subject to all legal requirements
being fulfilled. The approval of the transfer at, an undervalue, was agreed by
the Secretary of State and subject to the agreement of terms.
The purpose was to allow in the first instance borrowing against the site to
allow the stadium scheme to commence. The borrowing would be capped at a
maximum of £2million. Cabinet in December 2010 agreed to extend the
current offer of land up to a value of £2 million to the Wakefield and District
Community Trust (Wakefield Wildcats) value subject to the conditions to July
2011.
The offer naturally expired in July 2011 and was not renewed
During and since this time Wakefield Wildcats have been in administration
and has been sold twice.
February
2010
Outline planning application submitted by Yorkcourt Properties for mixed use
development at Newmarket Lane, including the community stadium, business
units, Storage & Distribution units, multi-use games areas, a hotel, a food unit
and associated roads and infrastructure.
March
2010
The Council agreed a loan guarantee with the Co-op Bank on 25 March 2010
for a loan taken out by the Trust for £150k for design fees for a community
stadium
October
2010
Planning & Highways Committee resolution to approve the development at
Newmarket Lane, subject to call-in by the government.
December
2010
As no proposals had been received by Wakefield Trinity, Wakefield Council
extends its £2m funding offer to July 2011.
Wakefield Trinity Stadium
Timeline of activity to April 2017
2
March
2011
The bank called upon the Council (as guarantor) to repay the loan in full.
July 2011 The £2m funding offer expired and was not renewed as the Trust did not
meet the conditions, nor did they ask for a further extension.
December
2011 -
The Secretary of State’s Public inquiry held into the Newmarket Lane
development.
September
2012
Local Development Framework development sites document was adopted by
the Council following a process to identify development sites to meet
additional need for warehousing and storage uses identified in the Core
Strategy. The Newmarket site being one of the sites. The Newmarket site and
other development sites were subject to an examination in public and
subsequently found to be “sound” by the inspector and incorporated into the
adopted Sites Allocations Document.
December
2012
Secretary of State decision made on Newmarket site.
This permission was approved by the Secretary of State following a 3 week
call in Inquiry. That permission was accompanied by a Section 106 Unilateral
Undertaking.
The Council were not party to that Unilateral Undertaking which was signed
by Yorkcourt and two other landowners, and set out their intention to let the
Stadium construction contract, provided the finance for the stadium was
available and once 60,000 sq. m of B8 warehousing had been built. A
planning condition was also attached to the Consent issued by the Secretary
of States that states:
“No more than 60,000m2
of the B8 development shall be occupied unless and
until the stadium is completed to its design capacity of 12,000 so as to be
capable of staging a Rugby Super League match attended by the public and
the stadium and its ancillary elements have received all necessary safety and
other certificates to allow it to be used for that purpose.”
The Unilateral Undertaking states that the Wakefield and District Community
Trust are responsible for acting as ‘facilitator’.
A copy of the Unilateral Undertaking can be found here:
cominoweb.wakefield.gov.uk/Plann ... =lg.Planni
ng&org.apache.shale.dialog.DIALOG_NAME=gfplanningsearch&SDescriptio
n=10/00225/OUT&viewdocs=true (Second document).
July 2013 Newcold planning application submitted.
A separate planning application was submitted by Yorkcourt Properties and
Newcold Ltd for a cold food distribution warehouse within the Newmarket site.
Wakefield Trinity Stadium
Timeline of activity to April 2017
3
This was submitted as a separate full planning application and was not linked
to the stadium development proposal that was given consent by the
Secretary of State.
The developer submitted a separate full planning application due to the
proposed size of the Newcold building which did not fall within the parameters
of the approved outline consent issued by the Secretary of State. The
decision to put in a new application was that of the developers not the
council, and the Council as the planning authority were duty bound to
consider a valid application as was the case.
Yorkcourt did not provide a Section 106 Agreement to link the Newcold
development with the funding of a community stadium. This was not required
as the site was allocated for employment uses within the Local Plan. This
was communicated to the Trust at a meeting with the Chief Executive and
Corporate Director for Regeneration and Economic Growth from Wakefield
Council at that time.
In line with the Council’s Statement of Community Involvement and statutory
regulations, there were two separate 21-day periods of public consultation
relating to the Newcold development. No objections to the Newcold planning
application from the Trust were received.
The development of the Newcold building does not prevent the 60,000 sq m
threshold of B8 development being met on the remainder of the site.
The Unilateral Undertaking offered by Yorkcourt and approved by the
Secretary of State, did not prohibit or limit any further planning applications or
development on the site.
The development of the stadium therefore can still be implemented
irrespective of the existence of the Newcold development.
October
2013
Newcold decision issued.
The Planning & Highways Committee made the decision to approve the
Newcold planning application.
The Committee Report on the Newcold proposal made clear, on page 11,
that the application was submitted as a standalone application and was not
covered by the outline planning consent for the stadium development or
planning conditions.
The report is available here.
cominoweb.wakefield.gov.uk/Plann ... =lg.Planni
ng&org.apache.shale.dialog.DIALOG_NAME=gfplanningsearch&SDescriptio
n=13/02001/FUL&viewdocs=true (First document).
Wakefield Trinity Stadium
Timeline of activity to April 2017
4
2015 Newcold development is completed. This includes the installation of a road
infrastructure that will provide essential access to the proposed location of a
new stadium.
The development created approximately 154 full time jobs in the district.
2013-17 Wakefield Council continues to meet with Wakefield Trinity, the Trust and
Yorkcourt to facilitate the progression of a new community stadium.
As part of ongoing work, the Council actively promotes the site to investors
coming into the district.


RankPostsTeam
International Star901
JoinedServiceReputation
Sep 201410 years
OnlineLast PostLast Page
Dec 2019Mar 2019LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Received the same. Nothing we haven't heard from them before. I guess it comes down to a fundamental disagreement between the trust/club and the council over whether Newcold should have counted towards the trigger point. Can only see it ending up in court now, which is probably for the best as at least we'd have a definitive answer either way.

RankPostsTeam
Club Captain24No
Team
Selected
JoinedServiceReputation
Mar 20178 years
OnlineLast PostLast Page
Aug 2024Aug 2024LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



this statement more than covers the council. Do I like it? No. Does anyone but the council like it? No. But newcold doesn't count to the required sqm development, the trust/club didn't object to this, there isn't the 106 agreement in place.so let's be honest here there is no stadium, there won't be a stadium unless privately funded and sir Rodney et al can all take pride in achieving so

RankPostsTeam
Club Coach8962
JoinedServiceReputation
Oct 200420 years
OnlineLast PostLast Page
May 2022Jun 2021LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED





RankPostsTeam
International Chairman1470
JoinedServiceReputation
Dec 200123 years
OnlineLast PostLast Page
Jan 1970Jun 2022LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Did I miss the bit where they explain why the application for Newcold was passed on a separate agreement without contributing to the build threshold? Or are they just using 'jobs' as an excuse?

RankPostsTeam
Club Coach7425
JoinedServiceReputation
May 200520 years
OnlineLast PostLast Page
Nov 2024Nov 2024LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



“At no point were current members of the stadium trust aware that the Newcold site would not count towards the Unilateral Agreement"
So, which ex member of the stadium trust was aware about the Newcold site? icon_smile.gif

RankPostsTeam
Club Captain24No
Team
Selected
JoinedServiceReputation
Mar 20178 years
OnlineLast PostLast Page
Aug 2024Aug 2024LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



so what's the trusts next move here?

RankPostsTeam
Club Coach36117
JoinedServiceReputation
Oct 200420 years
OnlineLast PostLast Page
Nov 2024Nov 2024LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Quote: BigJMolloy "this statement more than covers the council. Do I like it? No. Does anyone but the council like it? No. But newcold doesn't count to the required sqm development, the trust/club didn't object to this, there isn't the 106 agreement in place.so let's be honest here there is no stadium, there won't be a stadium unless privately funded and sir Rodney et al can all take pride in achieving so'"


The Trust didn't object because they (bar one) didn't know - if you're going to troll do it well please.

RankPostsTeam
Player Coach3011
JoinedServiceReputation
Jun 200519 years
OnlineLast PostLast Page
Nov 2022Sep 2022LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Quote: BigJMolloy "this statement more than covers the council. Do I like it? No. Does anyone but the council like it? No. But newcold doesn't count to the required sqm development, the trust/club didn't object to this, there isn't the 106 agreement in place.so let's be honest here there is no stadium, there won't be a stadium unless privately funded and sir Rodney et al can all take pride in achieving so'"

There is a s106 planning obligation.
They still haven't answered the question of why they as planning authority allowed newcold to come outside the planning obligation. Pleading innocence that "nobody objected" doesn't wash with me. As the authority charged with ensuring the planning obligation they shouldn't have created a loophole for the contractors.
They also claim that they've tried to attract businesses to the site over the last 4 years. I'd like to see the evidence.

RankPostsTeam
Club Coach7425
JoinedServiceReputation
May 200520 years
OnlineLast PostLast Page
Nov 2024Nov 2024LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Quote: BigJMolloy "this statement more than covers the council. Do I like it? No. Does anyone but the council like it? No. But newcold doesn't count to the required sqm development, the trust/club didn't object to this, there isn't the 106 agreement in place.so let's be honest here there is no stadium, there won't be a stadium unless privately funded and sir Rodney et al can all take pride in achieving so'"

Ted? icon_smile.gif

RankPostsTeam
Player Coach11580
JoinedServiceReputation
Oct 200717 years
OnlineLast PostLast Page
Nov 2024Sep 2023LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Quote: JINJER "Ted? Thought Ted went to Harrogate, not sure about Eric though!

RankPostsTeam
Club Captain320No
Team
Selected
JoinedServiceReputation
May 20169 years
OnlineLast PostLast Page
Aug 2022Aug 2022LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



If the trust didn't come forward with an objection (which I highly doubt) why would the council not turn it down? I'm not a planning expert however I'd like to think they have the power to do so?

RankPostsTeam
Club Coach7425
JoinedServiceReputation
May 200520 years
OnlineLast PostLast Page
Nov 2024Nov 2024LINK
Milestone Posts
0
100
Milestone Years
0510 1520 2530
Location
Signature
TO BE FIXED



Quote: chissitt "Thought Ted went to Harrogate, not sure about Eric though!'"

Hmmmm, multiple persona?

192 posts in 14 pages 
<<   PREV  NEXT   >>
Subscribe | Moderators: Admin, PopTart , kinleycat , Wildthing
192 posts in 14 pages 
<<   PREV  NEXT   >>
Subscribe | Moderators: Admin, PopTart , kinleycat , Wildthing



All views expressed are those of the author and not necessarily those of the RLFANS.COM or its subsites.

Whilst every effort is made to ensure that news stories, articles and images are correct, we cannot be held responsible for errors. However, if you feel any material on this website is copyrighted or incorrect in any way please contact us using the link at the top of the page so we can remove it or negotiate copyright permission.

RLFANS.COM, the owners of this website, is not responsible for the content of its sub-sites or posts, please email the author of this sub-site or post if you feel you find an article offensive or of a choice nature that you disagree with.

Copyright 1999 - 2024 RLFANS.COM

You must be 18+ to gamble, for more information and for help with gambling issues see https://www.begambleaware.org/.



Please Support RLFANS.COM


2.099609375:10
RLFANS Recent Posts
FORUM
LAST
POST
TOPIC
POSTER
POSTS
22m
Looking for a Good Time Connect with Local Ladies in Your T
hcc
1
Recent
Shirt reveal coming soon
Trojan Horse
50
Recent
2025 Kit
Marvin Goola
17
Recent
Ground Improvements
Trojan Horse
233
FORUM
LAST
VIEW
TOPIC
POSTER
POSTS
1m
Game - Song Titles
Boss Hog
40832
1m
Ground Improvements
Trojan Horse
233
2m
Looking for a Good Time Connect with Local Ladies in Your T
hcc
1
3m
Film game
karetaker
5859
4m
2025 Kit
Marvin Goola
17
4m
2025 Squad Numbers
Jake the Peg
12
5m
Castleford sack Lingard
FIL
17
5m
2025 Shirt
--[ WW ]--
27
6m
Salford placed in special measures
FIL
112
7m
2025 Recruitment
bowlinboy
228
FORUM
NEW
TOPICS
TOPIC
POSTER
POSTS
TODAY
Looking for a Good Time Connect with Local Ladies in Your T
hcc
1
TODAY
Matty Ashurst testimonial dinner
Big lads mat
1
TODAY
2025 Squad Numbers
Jake the Peg
12
TODAY
England Women Las Vegas train-on squad
RLFANS News
1
TODAY
Quiz night
H.G.S.A
1
TODAY
Co-Captains for 2025
MjM
15
TODAY
Cornwall has a new owner
CM Punk
2
TODAY
Callum Shaw
Wanderer
1
TODAY
Squad Numbers
phe13
4
TODAY
Rhinos squad numbers
Rixy
1
TODAY
Squad numbers
Warrior Wing
8
TODAY
Mat Crowther pre season update
Dunkirk Spir
1
TODAY
Mike Cooper podcast
Wires71
10
TODAY
Shirt reveal coming soon
Trojan Horse
50
TODAY
Opening Championship and League One Fixtures for 2025 Released
RLFANS News
1
NEWS ITEMS
VIEWS
POSTSONLINEREGISTRATIONSRECORD
19.65M 1,538 80,15614,103
LOGIN HERE
or REGISTER for more features!.

When you register you get access to the live match scores, live match chat and you can post in the discussions on the forums.
RLFANS Match Centre
 Thu 13th Feb 2025
     Mens Super League XXX-R1
20:00
Wigan
v
Leigh
 Fri 14th Feb 2025
     Mens Super League XXX-R1
20:00
Hull KR
v
Castleford
20:00
Catalans
v
Hull FC
 Sat 15th Feb 2025
     Mens Super League XXX-R1
15:00
Leeds
v
Wakefield
17:30
St.Helens
v
Salford
       Championship 2025-R1
18:00
Toulouse
v
Widnes
 Sun 16th Feb 2025
     Mens Super League XXX-R1
15:00
Huddersfield
v
Warrington
       Championship 2025-R1
15:00
Bradford
v
LondonB
15:00
Featherstone
v
Doncaster
15:00
Oldham
v
York
15:00
Sheffield
v
Halifax
15:00
Barrow
v
Hunslet
 Thu 20th Feb 2025
     Mens Super League XXX-R2
20:00
Wakefield
v
Hull KR
 Fri 21st Feb 2025
     Mens Super League XXX-R2
20:00
Warrington
v
Catalans
20:00
Hull FC
v
Wigan
 Sat 22nd Feb 2025
     Mens Super League XXX-R2
15:00
Salford
v
Leeds
20:00
Castleford
v
St.Helens
 Sun 23rd Feb 2025
     Mens Super League XXX-R2
14:30
Leigh
v
Huddersfield
       League One 2025-R1
15:00
Cornwall
v
Workington
15:00
Dewsbury
v
Crusaders
ALL SCORES PROVIDED BY RLFANS.COM (SETTINGS)
Matches on TV
Thu 13th Feb
SL
20:00
Wigan-Leigh
Fri 14th Feb
SL
20:00
Hull KR-Castleford
SL
20:00
Catalans-Hull FC
Sat 15th Feb
SL
15:00
Leeds-Wakefield
SL
17:30
St.Helens-Salford
Sun 16th Feb
SL
15:00
Huddersfield-Warrington
Thu 20th Feb
SL
20:00
Wakefield-Hull KR
Fri 21st Feb
SL
20:00
Warrington-Catalans
SL
20:00
Hull FC-Wigan
Sat 22nd Feb
SL
15:00
Salford-Leeds
SL
20:00
Castleford-St.Helens
Sun 23rd Feb
SL
14:30
Leigh-Huddersfield
Fri 28th Feb
SL
20:00
Huddersfield-Hull FC
SL
20:00
Hull KR-Salford
SL
20:00
Leigh-Catalans
Sat 1st Mar
SL
14:30
Wakefield-St.Helens
SL
21:30
Wigan-Warrington
Sun 2nd Mar
SL
15:00
Leeds-Castleford
Thu 6th Mar
SL
20:00
Hull FC-Leigh
Fri 7th Mar
SL
20:00
Castleford-Salford
This is an inplay table and live positions can change.
Mens Betfred Super League XXVIII ROUND : 1
 PLDFADIFFPTS
Wigan 29 768 338 430 48
Hull KR 29 731 344 387 44
Warrington 29 769 351 418 42
Leigh 29 580 442 138 33
Salford 28 556 561 -5 32
St.Helens 28 618 411 207 30
 
Catalans 27 475 427 48 30
Leeds 27 530 488 42 28
Huddersfield 27 468 658 -190 20
Castleford 27 425 735 -310 15
Hull FC 27 328 894 -566 6
LondonB 27 317 916 -599 6
This is an inplay table and live positions can change.
Betfred Championship 2024 ROUND : 1
 PLDFADIFFPTS
Wakefield 27 1032 275 757 52
Toulouse 26 765 388 377 37
Bradford 28 723 420 303 36
York 29 695 501 194 32
Widnes 27 561 502 59 29
Featherstone 27 634 525 109 28
 
Sheffield 26 626 526 100 28
Doncaster 26 498 619 -121 25
Halifax 26 509 650 -141 22
Batley 26 422 591 -169 22
Swinton 28 484 676 -192 20
Barrow 25 442 720 -278 19
Whitehaven 25 437 826 -389 18
Dewsbury 27 348 879 -531 4
Hunslet 1 6 10 -4 0
RLFANS Recent Posts
FORUM
LAST
POST
TOPIC
POSTER
POSTS
22m
Looking for a Good Time Connect with Local Ladies in Your T
hcc
1
Recent
Shirt reveal coming soon
Trojan Horse
50
Recent
2025 Kit
Marvin Goola
17
Recent
Ground Improvements
Trojan Horse
233
FORUM
LAST
VIEW
TOPIC
POSTER
POSTS
1m
Game - Song Titles
Boss Hog
40832
1m
Ground Improvements
Trojan Horse
233
2m
Looking for a Good Time Connect with Local Ladies in Your T
hcc
1
3m
Film game
karetaker
5859
4m
2025 Kit
Marvin Goola
17
4m
2025 Squad Numbers
Jake the Peg
12
5m
Castleford sack Lingard
FIL
17
5m
2025 Shirt
--[ WW ]--
27
6m
Salford placed in special measures
FIL
112
7m
2025 Recruitment
bowlinboy
228
FORUM
NEW
TOPICS
TOPIC
POSTER
POSTS
TODAY
Looking for a Good Time Connect with Local Ladies in Your T
hcc
1
TODAY
Matty Ashurst testimonial dinner
Big lads mat
1
TODAY
2025 Squad Numbers
Jake the Peg
12
TODAY
England Women Las Vegas train-on squad
RLFANS News
1
TODAY
Quiz night
H.G.S.A
1
TODAY
Co-Captains for 2025
MjM
15
TODAY
Cornwall has a new owner
CM Punk
2
TODAY
Callum Shaw
Wanderer
1
TODAY
Squad Numbers
phe13
4
TODAY
Rhinos squad numbers
Rixy
1
TODAY
Squad numbers
Warrior Wing
8
TODAY
Mat Crowther pre season update
Dunkirk Spir
1
TODAY
Mike Cooper podcast
Wires71
10
TODAY
Shirt reveal coming soon
Trojan Horse
50
TODAY
Opening Championship and League One Fixtures for 2025 Released
RLFANS News
1
NEWS ITEMS
VIEWS


Visit the RLFANS.COM SHOP
for more merchandise!